summaryrefslogtreecommitdiffstats
path: root/Documentation/scheduler/sched-deadline.rst
blob: 9fe4846079bbe0e0cb1273e969cf4cd233b41d5b (plain)
1
2
3
4
5
6
7
8
9
10
11
12
13
14
15
16
17
18
19
20
21
22
23
24
25
26
27
28
29
30
31
32
33
34
35
36
37
38
39
40
41
42
43
44
45
46
47
48
49
50
51
52
53
54
55
56
57
58
59
60
61
62
63
64
65
66
67
68
69
70
71
72
73
74
75
76
77
78
79
80
81
82
83
84
85
86
87
88
89
90
91
92
93
94
95
96
97
98
99
100
101
102
103
104
105
106
107
108
109
110
111
112
113
114
115
116
117
118
119
120
121
122
123
124
125
126
127
128
129
130
131
132
133
134
135
136
137
138
139
140
141
142
143
144
145
146
147
148
149
150
151
152
153
154
155
156
157
158
159
160
161
162
163
164
165
166
167
168
169
170
171
172
173
174
175
176
177
178
179
180
181
182
183
184
185
186
187
188
189
190
191
192
193
194
195
196
197
198
199
200
201
202
203
204
205
206
207
208
209
210
211
212
213
214
215
216
217
218
219
220
221
222
223
224
225
226
227
228
229
230
231
232
233
234
235
236
237
238
239
240
241
242
243
244
245
246
247
248
249
250
251
252
253
254
255
256
257
258
259
260
261
262
263
264
265
266
267
268
269
270
271
272
273
274
275
276
277
278
279
280
281
282
283
284
285
286
287
288
289
290
291
292
293
294
295
296
297
298
299
300
301
302
303
304
305
306
307
308
309
310
311
312
313
314
315
316
317
318
319
320
321
322
323
324
325
326
327
328
329
330
331
332
333
334
335
336
337
338
339
340
341
342
343
344
345
346
347
348
349
350
351
352
353
354
355
356
357
358
359
360
361
362
363
364
365
366
367
368
369
370
371
372
373
374
375
376
377
378
379
380
381
382
383
384
385
386
387
388
389
390
391
392
393
394
395
396
397
398
399
400
401
402
403
404
405
406
407
408
409
410
411
412
413
414
415
416
417
418
419
420
421
422
423
424
425
426
427
428
429
430
431
432
433
434
435
436
437
438
439
440
441
442
443
444
445
446
447
448
449
450
451
452
453
454
455
456
457
458
459
460
461
462
463
464
465
466
467
468
469
470
471
472
473
474
475
476
477
478
479
480
481
482
483
484
485
486
487
488
489
490
491
492
493
494
495
496
497
498
499
500
501
502
503
504
505
506
507
508
509
510
511
512
513
514
515
516
517
518
519
520
521
522
523
524
525
526
527
528
529
530
531
532
533
534
535
536
537
538
539
540
541
542
543
544
545
546
547
548
549
550
551
552
553
554
555
556
557
558
559
560
561
562
563
564
565
566
567
568
569
570
571
572
573
574
575
576
577
578
579
580
581
582
583
584
585
586
587
588
589
590
591
592
593
594
595
596
597
598
599
600
601
602
603
604
605
606
607
608
609
610
611
612
613
614
615
616
617
618
619
620
621
622
623
624
625
626
627
628
629
630
631
632
633
634
635
636
637
638
639
640
641
642
643
644
645
646
647
648
649
650
651
652
653
654
655
656
657
658
659
660
661
662
663
664
665
666
667
668
669
670
671
672
673
674
675
676
677
678
679
680
681
682
683
684
685
686
687
688
689
690
691
692
693
694
695
696
697
698
699
700
701
702
703
704
705
706
707
708
709
710
711
712
713
714
715
716
717
718
719
720
721
722
723
724
725
726
727
728
729
730
731
732
733
734
735
736
737
738
739
740
741
742
743
744
745
746
747
748
749
750
751
752
753
754
755
756
757
758
759
760
761
762
763
764
765
766
767
768
769
770
771
772
773
774
775
776
777
778
779
780
781
782
783
784
785
786
787
788
789
790
791
792
793
794
795
796
797
798
799
800
801
802
803
804
805
806
807
808
809
810
811
812
813
814
815
816
817
818
819
820
821
822
823
824
825
826
827
828
829
830
831
832
833
834
835
836
837
838
839
840
841
842
843
844
845
846
847
848
849
850
851
852
853
854
855
856
857
858
859
860
861
862
863
864
865
866
867
868
869
870
871
872
873
874
875
876
877
878
879
880
881
882
883
884
885
886
887
888
889
890
891
========================
Deadline Task Scheduling
========================

.. CONTENTS

    0. WARNING
    1. Overview
    2. Scheduling algorithm
      2.1 Main algorithm
      2.2 Bandwidth reclaiming
    3. Scheduling Real-Time Tasks
      3.1 Definitions
      3.2 Schedulability Analysis for Uniprocessor Systems
      3.3 Schedulability Analysis for Multiprocessor Systems
      3.4 Relationship with SCHED_DEADLINE Parameters
    4. Bandwidth management
      4.1 System-wide settings
      4.2 Task interface
      4.3 Default behavior
      4.4 Behavior of sched_yield()
    5. Tasks CPU affinity
      5.1 SCHED_DEADLINE and cpusets HOWTO
    6. Future plans
    A. Test suite
    B. Minimal main()


0. WARNING
==========

 Fiddling with these settings can result in an unpredictable or even unstable
 system behavior. As for -rt (group) scheduling, it is assumed that root users
 know what they're doing.


1. Overview
===========

 The SCHED_DEADLINE policy contained inside the sched_dl scheduling class is
 basically an implementation of the Earliest Deadline First (EDF) scheduling
 algorithm, augmented with a mechanism (called Constant Bandwidth Server, CBS)
 that makes it possible to isolate the behavior of tasks between each other.


2. Scheduling algorithm
=======================

2.1 Main algorithm
------------------

 SCHED_DEADLINE [18] uses three parameters, named "runtime", "period", and
 "deadline", to schedule tasks. A SCHED_DEADLINE task should receive
 "runtime" microseconds of execution time every "period" microseconds, and
 these "runtime" microseconds are available within "deadline" microseconds
 from the beginning of the period.  In order to implement this behavior,
 every time the task wakes up, the scheduler computes a "scheduling deadline"
 consistent with the guarantee (using the CBS[2,3] algorithm). Tasks are then
 scheduled using EDF[1] on these scheduling deadlines (the task with the
 earliest scheduling deadline is selected for execution). Notice that the
 task actually receives "runtime" time units within "deadline" if a proper
 "admission control" strategy (see Section "4. Bandwidth management") is used
 (clearly, if the system is overloaded this guarantee cannot be respected).

 Summing up, the CBS[2,3] algorithm assigns scheduling deadlines to tasks so
 that each task runs for at most its runtime every period, avoiding any
 interference between different tasks (bandwidth isolation), while the EDF[1]
 algorithm selects the task with the earliest scheduling deadline as the one
 to be executed next. Thanks to this feature, tasks that do not strictly comply
 with the "traditional" real-time task model (see Section 3) can effectively
 use the new policy.

 In more details, the CBS algorithm assigns scheduling deadlines to
 tasks in the following way:

  - Each SCHED_DEADLINE task is characterized by the "runtime",
    "deadline", and "period" parameters;

  - The state of the task is described by a "scheduling deadline", and
    a "remaining runtime". These two parameters are initially set to 0;

  - When a SCHED_DEADLINE task wakes up (becomes ready for execution),
    the scheduler checks if::

                 remaining runtime                  runtime
        ----------------------------------    >    ---------
        scheduling deadline - current time           period

    then, if the scheduling deadline is smaller than the current time, or
    this condition is verified, the scheduling deadline and the
    remaining runtime are re-initialized as

         scheduling deadline = current time + deadline
         remaining runtime = runtime

    otherwise, the scheduling deadline and the remaining runtime are
    left unchanged;

  - When a SCHED_DEADLINE task executes for an amount of time t, its
    remaining runtime is decreased as::

         remaining runtime = remaining runtime - t

    (technically, the runtime is decreased at every tick, or when the
    task is descheduled / preempted);

  - When the remaining runtime becomes less or equal than 0, the task is
    said to be "throttled" (also known as "depleted" in real-time literature)
    and cannot be scheduled until its scheduling deadline. The "replenishment
    time" for this task (see next item) is set to be equal to the current
    value of the scheduling deadline;

  - When the current time is equal to the replenishment time of a
    throttled task, the scheduling deadline and the remaining runtime are
    updated as::

         scheduling deadline = scheduling deadline + period
         remaining runtime = remaining runtime + runtime

 The SCHED_FLAG_DL_OVERRUN flag in sched_attr's sched_flags field allows a task
 to get informed about runtime overruns through the delivery of SIGXCPU
 signals.


2.2 Bandwidth reclaiming
------------------------

 Bandwidth reclaiming for deadline tasks is based on the GRUB (Greedy
 Reclamation of Unused Bandwidth) algorithm [15, 16, 17] and it is enabled
 when flag SCHED_FLAG_RECLAIM is set.

 The following diagram illustrates the state names for tasks handled by GRUB::

                             ------------
                 (d)        |   Active   |
              ------------->|            |
              |             | Contending |
              |              ------------
              |                A      |
          ----------           |      |
         |          |          |      |
         | Inactive |          |(b)   | (a)
         |          |          |      |
          ----------           |      |
              A                |      V
              |              ------------
              |             |   Active   |
              --------------|     Non    |
                 (c)        | Contending |
                             ------------

 A task can be in one of the following states:

  - ActiveContending: if it is ready for execution (or executing);

  - ActiveNonContending: if it just blocked and has not yet surpassed the 0-lag
    time;

  - Inactive: if it is blocked and has surpassed the 0-lag time.

 State transitions:

  (a) When a task blocks, it does not become immediately inactive since its
      bandwidth cannot be immediately reclaimed without breaking the
      real-time guarantees. It therefore enters a transitional state called
      ActiveNonContending. The scheduler arms the "inactive timer" to fire at
      the 0-lag time, when the task's bandwidth can be reclaimed without
      breaking the real-time guarantees.

      The 0-lag time for a task entering the ActiveNonContending state is
      computed as::

                        (runtime * dl_period)
             deadline - ---------------------
                             dl_runtime

      where runtime is the remaining runtime, while dl_runtime and dl_period
      are the reservation parameters.

  (b) If the task wakes up before the inactive timer fires, the task re-enters
      the ActiveContending state and the "inactive timer" is canceled.
      In addition, if the task wakes up on a different runqueue, then
      the task's utilization must be removed from the previous runqueue's active
      utilization and must be added to the new runqueue's active utilization.
      In order to avoid races between a task waking up on a runqueue while the
      "inactive timer" is running on a different CPU, the "dl_non_contending"
      flag is used to indicate that a task is not on a runqueue but is active
      (so, the flag is set when the task blocks and is cleared when the
      "inactive timer" fires or when the task  wakes up).

  (c) When the "inactive timer" fires, the task enters the Inactive state and
      its utilization is removed from the runqueue's active utilization.

  (d) When an inactive task wakes up, it enters the ActiveContending state and
      its utilization is added to the active utilization of the runqueue where
      it has been enqueued.

 For each runqueue, the algorithm GRUB keeps track of two different bandwidths:

  - Active bandwidth (running_bw): this is the sum of the bandwidths of all
    tasks in active state (i.e., ActiveContending or ActiveNonContending);

  - Total bandwidth (this_bw): this is the sum of all tasks "belonging" to the
    runqueue, including the tasks in Inactive state.

  - Maximum usable bandwidth (max_bw): This is the maximum bandwidth usable by
    deadline tasks and is currently set to the RT capacity.


 The algorithm reclaims the bandwidth of the tasks in Inactive state.
 It does so by decrementing the runtime of the executing task Ti at a pace equal
 to

           dq = -(max{ Ui, (Umax - Uinact - Uextra) } / Umax) dt

 where:

  - Ui is the bandwidth of task Ti;
  - Umax is the maximum reclaimable utilization (subjected to RT throttling
    limits);
  - Uinact is the (per runqueue) inactive utilization, computed as
    (this_bq - running_bw);
  - Uextra is the (per runqueue) extra reclaimable utilization
    (subjected to RT throttling limits).


 Let's now see a trivial example of two deadline tasks with runtime equal
 to 4 and period equal to 8 (i.e., bandwidth equal to 0.5)::

         A            Task T1
         |
         |                               |
         |                               |
         |--------                       |----
         |       |                       V
         |---|---|---|---|---|---|---|---|--------->t
         0   1   2   3   4   5   6   7   8


         A            Task T2
         |
         |                               |
         |                               |
         |       ------------------------|
         |       |                       V
         |---|---|---|---|---|---|---|---|--------->t
         0   1   2   3   4   5   6   7   8


         A            running_bw
         |
       1 -----------------               ------
         |               |               |
      0.5-               -----------------
         |                               |
         |---|---|---|---|---|---|---|---|--------->t
         0   1   2   3   4   5   6   7   8


  - Time t = 0:

    Both tasks are ready for execution and therefore in ActiveContending state.
    Suppose Task T1 is the first task to start execution.
    Since there are no inactive tasks, its runtime is decreased as dq = -1 dt.

  - Time t = 2:

    Suppose that task T1 blocks
    Task T1 therefore enters the ActiveNonContending state. Since its remaining
    runtime is equal to 2, its 0-lag time is equal to t = 4.
    Task T2 start execution, with runtime still decreased as dq = -1 dt since
    there are no inactive tasks.

  - Time t = 4:

    This is the 0-lag time for Task T1. Since it didn't woken up in the
    meantime, it enters the Inactive state. Its bandwidth is removed from
    running_bw.
    Task T2 continues its execution. However, its runtime is now decreased as
    dq = - 0.5 dt because Uinact = 0.5.
    Task T2 therefore reclaims the bandwidth unused by Task T1.

  - Time t = 8:

    Task T1 wakes up. It enters the ActiveContending state again, and the
    running_bw is incremented.


2.3 Energy-aware scheduling
---------------------------

 When cpufreq's schedutil governor is selected, SCHED_DEADLINE implements the
 GRUB-PA [19] algorithm, reducing the CPU operating frequency to the minimum
 value that still allows to meet the deadlines. This behavior is currently
 implemented only for ARM architectures.

 A particular care must be taken in case the time needed for changing frequency
 is of the same order of magnitude of the reservation period. In such cases,
 setting a fixed CPU frequency results in a lower amount of deadline misses.


3. Scheduling Real-Time Tasks
=============================



 ..  BIG FAT WARNING ******************************************************

 .. warning::

   This section contains a (not-thorough) summary on classical deadline
   scheduling theory, and how it applies to SCHED_DEADLINE.
   The reader can "safely" skip to Section 4 if only interested in seeing
   how the scheduling policy can be used. Anyway, we strongly recommend
   to come back here and continue reading (once the urge for testing is
   satisfied :P) to be sure of fully understanding all technical details.

 .. ************************************************************************

 There are no limitations on what kind of task can exploit this new
 scheduling discipline, even if it must be said that it is particularly
 suited for periodic or sporadic real-time tasks that need guarantees on their
 timing behavior, e.g., multimedia, streaming, control applications, etc.

3.1 Definitions
------------------------

 A typical real-time task is composed of a repetition of computation phases
 (task instances, or jobs) which are activated on a periodic or sporadic
 fashion.
 Each job J_j (where J_j is the j^th job of the task) is characterized by an
 arrival time r_j (the time when the job starts), an amount of computation
 time c_j needed to finish the job, and a job absolute deadline d_j, which
 is the time within which the job should be finished. The maximum execution
 time max{c_j} is called "Worst Case Execution Time" (WCET) for the task.
 A real-time task can be periodic with period P if r_{j+1} = r_j + P, or
 sporadic with minimum inter-arrival time P is r_{j+1} >= r_j + P. Finally,
 d_j = r_j + D, where D is the task's relative deadline.
 Summing up, a real-time task can be described as

	Task = (WCET, D, P)

 The utilization of a real-time task is defined as the ratio between its
 WCET and its period (or minimum inter-arrival time), and represents
 the fraction of CPU time needed to execute the task.

 If the total utilization U=sum(WCET_i/P_i) is larger than M (with M equal
 to the number of CPUs), then the scheduler is unable to respect all the
 deadlines.
 Note that total utilization is defined as the sum of the utilizations
 WCET_i/P_i over all the real-time tasks in the system. When considering
 multiple real-time tasks, the parameters of the i-th task are indicated
 with the "_i" suffix.
 Moreover, if the total utilization is larger than M, then we risk starving
 non- real-time tasks by real-time tasks.
 If, instead, the total utilization is smaller than M, then non real-time
 tasks will not be starved and the system might be able to respect all the
 deadlines.
 As a matter of fact, in this case it is possible to provide an upper bound
 for tardiness (defined as the maximum between 0 and the difference
 between the finishing time of a job and its absolute deadline).
 More precisely, it can be proven that using a global EDF scheduler the
 maximum tardiness of each task is smaller or equal than

	((M − 1) · WCET_max − WCET_min)/(M − (M − 2) · U_max) + WCET_max

 where WCET_max = max{WCET_i} is the maximum WCET, WCET_min=min{WCET_i}
 is the minimum WCET, and U_max = max{WCET_i/P_i} is the maximum
 utilization[12].

3.2 Schedulability Analysis for Uniprocessor Systems
----------------------------------------------------

 If M=1 (uniprocessor system), or in case of partitioned scheduling (each
 real-time task is statically assigned to one and only one CPU), it is
 possible to formally check if all the deadlines are respected.
 If D_i = P_i for all tasks, then EDF is able to respect all the deadlines
 of all the tasks executing on a CPU if and only if the total utilization
 of the tasks running on such a CPU is smaller or equal than 1.
 If D_i != P_i for some task, then it is possible to define the density of
 a task as WCET_i/min{D_i,P_i}, and EDF is able to respect all the deadlines
 of all the tasks running on a CPU if the sum of the densities of the tasks
 running on such a CPU is smaller or equal than 1:

	sum(WCET_i / min{D_i, P_i}) <= 1

 It is important to notice that this condition is only sufficient, and not
 necessary: there are task sets that are schedulable, but do not respect the
 condition. For example, consider the task set {Task_1,Task_2} composed by
 Task_1=(50ms,50ms,100ms) and Task_2=(10ms,100ms,100ms).
 EDF is clearly able to schedule the two tasks without missing any deadline
 (Task_1 is scheduled as soon as it is released, and finishes just in time
 to respect its deadline; Task_2 is scheduled immediately after Task_1, hence
 its response time cannot be larger than 50ms + 10ms = 60ms) even if

	50 / min{50,100} + 10 / min{100, 100} = 50 / 50 + 10 / 100 = 1.1

 Of course it is possible to test the exact schedulability of tasks with
 D_i != P_i (checking a condition that is both sufficient and necessary),
 but this cannot be done by comparing the total utilization or density with
 a constant. Instead, the so called "processor demand" approach can be used,
 computing the total amount of CPU time h(t) needed by all the tasks to
 respect all of their deadlines in a time interval of size t, and comparing
 such a time with the interval size t. If h(t) is smaller than t (that is,
 the amount of time needed by the tasks in a time interval of size t is
 smaller than the size of the interval) for all the possible values of t, then
 EDF is able to schedule the tasks respecting all of their deadlines. Since
 performing this check for all possible values of t is impossible, it has been
 proven[4,5,6] that it is sufficient to perform the test for values of t
 between 0 and a maximum value L. The cited papers contain all of the
 mathematical details and explain how to compute h(t) and L.
 In any case, this kind of analysis is too complex as well as too
 time-consuming to be performed on-line. Hence, as explained in Section
 4 Linux uses an admission test based on the tasks' utilizations.

3.3 Schedulability Analysis for Multiprocessor Systems
------------------------------------------------------

 On multiprocessor systems with global EDF scheduling (non partitioned
 systems), a sufficient test for schedulability can not be based on the
 utilizations or densities: it can be shown that even if D_i = P_i task
 sets with utilizations slightly larger than 1 can miss deadlines regardless
 of the number of CPUs.

 Consider a set {Task_1,...Task_{M+1}} of M+1 tasks on a system with M
 CPUs, with the first task Task_1=(P,P,P) having period, relative deadline
 and WCET equal to P. The remaining M tasks Task_i=(e,P-1,P-1) have an
 arbitrarily small worst case execution time (indicated as "e" here) and a
 period smaller than the one of the first task. Hence, if all the tasks
 activate at the same time t, global EDF schedules these M tasks first
 (because their absolute deadlines are equal to t + P - 1, hence they are
 smaller than the absolute deadline of Task_1, which is t + P). As a
 result, Task_1 can be scheduled only at time t + e, and will finish at
 time t + e + P, after its absolute deadline. The total utilization of the
 task set is U = M · e / (P - 1) + P / P = M · e / (P - 1) + 1, and for small
 values of e this can become very close to 1. This is known as "Dhall's
 effect"[7]. Note: the example in the original paper by Dhall has been
 slightly simplified here (for example, Dhall more correctly computed
 lim_{e->0}U).

 More complex schedulability tests for global EDF have been developed in
 real-time literature[8,9], but they are not based on a simple comparison
 between total utilization (or density) and a fixed constant. If all tasks
 have D_i = P_i, a sufficient schedulability condition can be expressed in
 a simple way:

	sum(WCET_i / P_i) <= M - (M - 1) · U_max

 where U_max = max{WCET_i / P_i}[10]. Notice that for U_max = 1,
 M - (M - 1) · U_max becomes M - M + 1 = 1 and this schedulability condition
 just confirms the Dhall's effect. A more complete survey of the literature
 about schedulability tests for multi-processor real-time scheduling can be
 found in [11].

 As seen, enforcing that the total utilization is smaller than M does not
 guarantee that global EDF schedules the tasks without missing any deadline
 (in other words, global EDF is not an optimal scheduling algorithm). However,
 a total utilization smaller than M is enough to guarantee that non real-time
 tasks are not starved and that the tardiness of real-time tasks has an upper
 bound[12] (as previously noted). Different bounds on the maximum tardiness
 experienced by real-time tasks have been developed in various papers[13,14],
 but the theoretical result that is important for SCHED_DEADLINE is that if
 the total utilization is smaller or equal than M then the response times of
 the tasks are limited.

3.4 Relationship with SCHED_DEADLINE Parameters
-----------------------------------------------

 Finally, it is important to understand the relationship between the
 SCHED_DEADLINE scheduling parameters described in Section 2 (runtime,
 deadline and period) and the real-time task parameters (WCET, D, P)
 described in this section. Note that the tasks' temporal constraints are
 represented by its absolute deadlines d_j = r_j + D described above, while
 SCHED_DEADLINE schedules the tasks according to scheduling deadlines (see
 Section 2).
 If an admission test is used to guarantee that the scheduling deadlines
 are respected, then SCHED_DEADLINE can be used to schedule real-time tasks
 guaranteeing that all the jobs' deadlines of a task are respected.
 In order to do this, a task must be scheduled by setting:

  - runtime >= WCET
  - deadline = D
  - period <= P

 IOW, if runtime >= WCET and if period is <= P, then the scheduling deadlines
 and the absolute deadlines (d_j) coincide, so a proper admission control
 allows to respect the jobs' absolute deadlines for this task (this is what is
 called "hard schedulability property" and is an extension of Lemma 1 of [2]).
 Notice that if runtime > deadline the admission control will surely reject
 this task, as it is not possible to respect its temporal constraints.

 References:

  1 - C. L. Liu and J. W. Layland. Scheduling algorithms for multiprogram-
      ming in a hard-real-time environment. Journal of the Association for
      Computing Machinery, 20(1), 1973.
  2 - L. Abeni , G. Buttazzo. Integrating Multimedia Applications in Hard
      Real-Time Systems. Proceedings of the 19th IEEE Real-time Systems
      Symposium, 1998. http://retis.sssup.it/~giorgio/paps/1998/rtss98-cbs.pdf
  3 - L. Abeni. Server Mechanisms for Multimedia Applications. ReTiS Lab
      Technical Report. http://disi.unitn.it/~abeni/tr-98-01.pdf
  4 - J. Y. Leung and M.L. Merril. A Note on Preemptive Scheduling of
      Periodic, Real-Time Tasks. Information Processing Letters, vol. 11,
      no. 3, pp. 115-118, 1980.
  5 - S. K. Baruah, A. K. Mok and L. E. Rosier. Preemptively Scheduling
      Hard-Real-Time Sporadic Tasks on One Processor. Proceedings of the
      11th IEEE Real-time Systems Symposium, 1990.
  6 - S. K. Baruah, L. E. Rosier and R. R. Howell. Algorithms and Complexity
      Concerning the Preemptive Scheduling of Periodic Real-Time tasks on
      One Processor. Real-Time Systems Journal, vol. 4, no. 2, pp 301-324,
      1990.
  7 - S. J. Dhall and C. L. Liu. On a real-time scheduling problem. Operations
      research, vol. 26, no. 1, pp 127-140, 1978.
  8 - T. Baker. Multiprocessor EDF and Deadline Monotonic Schedulability
      Analysis. Proceedings of the 24th IEEE Real-Time Systems Symposium, 2003.
  9 - T. Baker. An Analysis of EDF Schedulability on a Multiprocessor.
      IEEE Transactions on Parallel and Distributed Systems, vol. 16, no. 8,
      pp 760-768, 2005.
  10 - J. Goossens, S. Funk and S. Baruah, Priority-Driven Scheduling of
       Periodic Task Systems on Multiprocessors. Real-Time Systems Journal,
       vol. 25, no. 2–3, pp. 187–205, 2003.
  11 - R. Davis and A. Burns. A Survey of Hard Real-Time Scheduling for
       Multiprocessor Systems. ACM Computing Surveys, vol. 43, no. 4, 2011.
       http://www-users.cs.york.ac.uk/~robdavis/papers/MPSurveyv5.0.pdf
  12 - U. C. Devi and J. H. Anderson. Tardiness Bounds under Global EDF
       Scheduling on a Multiprocessor. Real-Time Systems Journal, vol. 32,
       no. 2, pp 133-189, 2008.
  13 - P. Valente and G. Lipari. An Upper Bound to the Lateness of Soft
       Real-Time Tasks Scheduled by EDF on Multiprocessors. Proceedings of
       the 26th IEEE Real-Time Systems Symposium, 2005.
  14 - J. Erickson, U. Devi and S. Baruah. Improved tardiness bounds for
       Global EDF. Proceedings of the 22nd Euromicro Conference on
       Real-Time Systems, 2010.
  15 - G. Lipari, S. Baruah, Greedy reclamation of unused bandwidth in
       constant-bandwidth servers, 12th IEEE Euromicro Conference on Real-Time
       Systems, 2000.
  16 - L. Abeni, J. Lelli, C. Scordino, L. Palopoli, Greedy CPU reclaiming for
       SCHED DEADLINE. In Proceedings of the Real-Time Linux Workshop (RTLWS),
       Dusseldorf, Germany, 2014.
  17 - L. Abeni, G. Lipari, A. Parri, Y. Sun, Multicore CPU reclaiming: parallel
       or sequential?. In Proceedings of the 31st Annual ACM Symposium on Applied
       Computing, 2016.
  18 - J. Lelli, C. Scordino, L. Abeni, D. Faggioli, Deadline scheduling in the
       Linux kernel, Software: Practice and Experience, 46(6): 821-839, June
       2016.
  19 - C. Scordino, L. Abeni, J. Lelli, Energy-Aware Real-Time Scheduling in
       the Linux Kernel, 33rd ACM/SIGAPP Symposium On Applied Computing (SAC
       2018), Pau, France, April 2018.


4. Bandwidth management
=======================

 As previously mentioned, in order for -deadline scheduling to be
 effective and useful (that is, to be able to provide "runtime" time units
 within "deadline"), it is important to have some method to keep the allocation
 of the available fractions of CPU time to the various tasks under control.
 This is usually called "admission control" and if it is not performed, then
 no guarantee can be given on the actual scheduling of the -deadline tasks.

 As already stated in Section 3, a necessary condition to be respected to
 correctly schedule a set of real-time tasks is that the total utilization
 is smaller than M. When talking about -deadline tasks, this requires that
 the sum of the ratio between runtime and period for all tasks is smaller
 than M. Notice that the ratio runtime/period is equivalent to the utilization
 of a "traditional" real-time task, and is also often referred to as
 "bandwidth".
 The interface used to control the CPU bandwidth that can be allocated
 to -deadline tasks is similar to the one already used for -rt
 tasks with real-time group scheduling (a.k.a. RT-throttling - see
 Documentation/scheduler/sched-rt-group.rst), and is based on readable/
 writable control files located in procfs (for system wide settings).
 Notice that per-group settings (controlled through cgroupfs) are still not
 defined for -deadline tasks, because more discussion is needed in order to
 figure out how we want to manage SCHED_DEADLINE bandwidth at the task group
 level.

 A main difference between deadline bandwidth management and RT-throttling
 is that -deadline tasks have bandwidth on their own (while -rt ones don't!),
 and thus we don't need a higher level throttling mechanism to enforce the
 desired bandwidth. In other words, this means that interface parameters are
 only used at admission control time (i.e., when the user calls
 sched_setattr()). Scheduling is then performed considering actual tasks'
 parameters, so that CPU bandwidth is allocated to SCHED_DEADLINE tasks
 respecting their needs in terms of granularity. Therefore, using this simple
 interface we can put a cap on total utilization of -deadline tasks (i.e.,
 \Sum (runtime_i / period_i) < global_dl_utilization_cap).

4.1 System wide settings
------------------------

 The system wide settings are configured under the /proc virtual file system.

 For now the -rt knobs are used for -deadline admission control and the
 -deadline runtime is accounted against the -rt runtime. We realize that this
 isn't entirely desirable; however, it is better to have a small interface for
 now, and be able to change it easily later. The ideal situation (see 5.) is to
 run -rt tasks from a -deadline server; in which case the -rt bandwidth is a
 direct subset of dl_bw.

 This means that, for a root_domain comprising M CPUs, -deadline tasks
 can be created while the sum of their bandwidths stays below:

   M * (sched_rt_runtime_us / sched_rt_period_us)

 It is also possible to disable this bandwidth management logic, and
 be thus free of oversubscribing the system up to any arbitrary level.
 This is done by writing -1 in /proc/sys/kernel/sched_rt_runtime_us.


4.2 Task interface
------------------

 Specifying a periodic/sporadic task that executes for a given amount of
 runtime at each instance, and that is scheduled according to the urgency of
 its own timing constraints needs, in general, a way of declaring:

  - a (maximum/typical) instance execution time,
  - a minimum interval between consecutive instances,
  - a time constraint by which each instance must be completed.

 Therefore:

  * a new struct sched_attr, containing all the necessary fields is
    provided;
  * the new scheduling related syscalls that manipulate it, i.e.,
    sched_setattr() and sched_getattr() are implemented.

 For debugging purposes, the leftover runtime and absolute deadline of a
 SCHED_DEADLINE task can be retrieved through /proc/<pid>/sched (entries
 dl.runtime and dl.deadline, both values in ns). A programmatic way to
 retrieve these values from production code is under discussion.


4.3 Default behavior
---------------------

 The default value for SCHED_DEADLINE bandwidth is to have rt_runtime equal to
 950000. With rt_period equal to 1000000, by default, it means that -deadline
 tasks can use at most 95%, multiplied by the number of CPUs that compose the
 root_domain, for each root_domain.
 This means that non -deadline tasks will receive at least 5% of the CPU time,
 and that -deadline tasks will receive their runtime with a guaranteed
 worst-case delay respect to the "deadline" parameter. If "deadline" = "period"
 and the cpuset mechanism is used to implement partitioned scheduling (see
 Section 5), then this simple setting of the bandwidth management is able to
 deterministically guarantee that -deadline tasks will receive their runtime
 in a period.

 Finally, notice that in order not to jeopardize the admission control a
 -deadline task cannot fork.


4.4 Behavior of sched_yield()
-----------------------------

 When a SCHED_DEADLINE task calls sched_yield(), it gives up its
 remaining runtime and is immediately throttled, until the next
 period, when its runtime will be replenished (a special flag
 dl_yielded is set and used to handle correctly throttling and runtime
 replenishment after a call to sched_yield()).

 This behavior of sched_yield() allows the task to wake-up exactly at
 the beginning of the next period. Also, this may be useful in the
 future with bandwidth reclaiming mechanisms, where sched_yield() will
 make the leftoever runtime available for reclamation by other
 SCHED_DEADLINE tasks.


5. Tasks CPU affinity
=====================

 -deadline tasks cannot have an affinity mask smaller that the entire
 root_domain they are created on. However, affinities can be specified
 through the cpuset facility (Documentation/admin-guide/cgroup-v1/cpusets.rst).

5.1 SCHED_DEADLINE and cpusets HOWTO
------------------------------------

 An example of a simple configuration (pin a -deadline task to CPU0)
 follows (rt-app is used to create a -deadline task)::

   mkdir /dev/cpuset
   mount -t cgroup -o cpuset cpuset /dev/cpuset
   cd /dev/cpuset
   mkdir cpu0
   echo 0 > cpu0/cpuset.cpus
   echo 0 > cpu0/cpuset.mems
   echo 1 > cpuset.cpu_exclusive
   echo 0 > cpuset.sched_load_balance
   echo 1 > cpu0/cpuset.cpu_exclusive
   echo 1 > cpu0/cpuset.mem_exclusive
   echo $$ > cpu0/tasks
   rt-app -t 100000:10000:d:0 -D5 # it is now actually superfluous to specify
				  # task affinity

6. Future plans
===============

 Still missing:

  - programmatic way to retrieve current runtime and absolute deadline
  - refinements to deadline inheritance, especially regarding the possibility
    of retaining bandwidth isolation among non-interacting tasks. This is
    being studied from both theoretical and practical points of view, and
    hopefully we should be able to produce some demonstrative code soon;
  - (c)group based bandwidth management, and maybe scheduling;
  - access control for non-root users (and related security concerns to
    address), which is the best way to allow unprivileged use of the mechanisms
    and how to prevent non-root users "cheat" the system?

 As already discussed, we are planning also to merge this work with the EDF
 throttling patches [https://lore.kernel.org/r/cover.1266931410.git.fabio@helm.retis] but we still are in
 the preliminary phases of the merge and we really seek feedback that would
 help us decide on the direction it should take.

Appendix A. Test suite
======================

 The SCHED_DEADLINE policy can be easily tested using two applications that
 are part of a wider Linux Scheduler validation suite. The suite is
 available as a GitHub repository: https://github.com/scheduler-tools.

 The first testing application is called rt-app and can be used to
 start multiple threads with specific parameters. rt-app supports
 SCHED_{OTHER,FIFO,RR,DEADLINE} scheduling policies and their related
 parameters (e.g., niceness, priority, runtime/deadline/period). rt-app
 is a valuable tool, as it can be used to synthetically recreate certain
 workloads (maybe mimicking real use-cases) and evaluate how the scheduler
 behaves under such workloads. In this way, results are easily reproducible.
 rt-app is available at: https://github.com/scheduler-tools/rt-app.

 Thread parameters can be specified from the command line, with something like
 this::

  # rt-app -t 100000:10000:d -t 150000:20000:f:10 -D5

 The above creates 2 threads. The first one, scheduled by SCHED_DEADLINE,
 executes for 10ms every 100ms. The second one, scheduled at SCHED_FIFO
 priority 10, executes for 20ms every 150ms. The test will run for a total
 of 5 seconds.

 More interestingly, configurations can be described with a json file that
 can be passed as input to rt-app with something like this::

  # rt-app my_config.json

 The parameters that can be specified with the second method are a superset
 of the command line options. Please refer to rt-app documentation for more
 details (`<rt-app-sources>/doc/*.json`).

 The second testing application is a modification of schedtool, called
 schedtool-dl, which can be used to setup SCHED_DEADLINE parameters for a
 certain pid/application. schedtool-dl is available at:
 https://github.com/scheduler-tools/schedtool-dl.git.

 The usage is straightforward::

  # schedtool -E -t 10000000:100000000 -e ./my_cpuhog_app

 With this, my_cpuhog_app is put to run inside a SCHED_DEADLINE reservation
 of 10ms every 100ms (note that parameters are expressed in microseconds).
 You can also use schedtool to create a reservation for an already running
 application, given that you know its pid::

  # schedtool -E -t 10000000:100000000 my_app_pid

Appendix B. Minimal main()
==========================

 We provide in what follows a simple (ugly) self-contained code snippet
 showing how SCHED_DEADLINE reservations can be created by a real-time
 application developer::

   #define _GNU_SOURCE
   #include <unistd.h>
   #include <stdio.h>
   #include <stdlib.h>
   #include <string.h>
   #include <time.h>
   #include <linux/unistd.h>
   #include <linux/kernel.h>
   #include <linux/types.h>
   #include <sys/syscall.h>
   #include <pthread.h>

   #define gettid() syscall(__NR_gettid)

   #define SCHED_DEADLINE	6

   /* XXX use the proper syscall numbers */
   #ifdef __x86_64__
   #define __NR_sched_setattr		314
   #define __NR_sched_getattr		315
   #endif

   #ifdef __i386__
   #define __NR_sched_setattr		351
   #define __NR_sched_getattr		352
   #endif

   #ifdef __arm__
   #define __NR_sched_setattr		380
   #define __NR_sched_getattr		381
   #endif

   static volatile int done;

   struct sched_attr {
	__u32 size;

	__u32 sched_policy;
	__u64 sched_flags;

	/* SCHED_NORMAL, SCHED_BATCH */
	__s32 sched_nice;

	/* SCHED_FIFO, SCHED_RR */
	__u32 sched_priority;

	/* SCHED_DEADLINE (nsec) */
	__u64 sched_runtime;
	__u64 sched_deadline;
	__u64 sched_period;
   };

   int sched_setattr(pid_t pid,
		  const struct sched_attr *attr,
		  unsigned int flags)
   {
	return syscall(__NR_sched_setattr, pid, attr, flags);
   }

   int sched_getattr(pid_t pid,
		  struct sched_attr *attr,
		  unsigned int size,
		  unsigned int flags)
   {
	return syscall(__NR_sched_getattr, pid, attr, size, flags);
   }

   void *run_deadline(void *data)
   {
	struct sched_attr attr;
	int x = 0;
	int ret;
	unsigned int flags = 0;

	printf("deadline thread started [%ld]\n", gettid());

	attr.size = sizeof(attr);
	attr.sched_flags = 0;
	attr.sched_nice = 0;
	attr.sched_priority = 0;

	/* This creates a 10ms/30ms reservation */
	attr.sched_policy = SCHED_DEADLINE;
	attr.sched_runtime = 10 * 1000 * 1000;
	attr.sched_period = attr.sched_deadline = 30 * 1000 * 1000;

	ret = sched_setattr(0, &attr, flags);
	if (ret < 0) {
		done = 0;
		perror("sched_setattr");
		exit(-1);
	}

	while (!done) {
		x++;
	}

	printf("deadline thread dies [%ld]\n", gettid());
	return NULL;
   }

   int main (int argc, char **argv)
   {
	pthread_t thread;

	printf("main thread [%ld]\n", gettid());

	pthread_create(&thread, NULL, run_deadline, NULL);

	sleep(10);

	done = 1;
	pthread_join(thread, NULL);

	printf("main dies [%ld]\n", gettid());
	return 0;
   }